LPP is Not Economically Feasible: Spectrum Opinion

7/31/20; by Helene Jorgensen

“Zack Renstrom, general manager of the WCWCD, is incorrect when he writes that “two independent studies confirmed the Lake Powell Pipeline is economically feasible and affordable” (Letter to Editor, July 19). The State of Utah’s audit relied on 2015 cost estimates by the consulting company MWH Global; and the cost estimates in the draft environmental impact statement were the same MWH cost estimates updated for inflation by the consulting company Stantec. MWH Global and Stantec merged in 2016…”

Read the entire article here: https://www.thespectrum.com/story/opinion/2020/07/31/letter-editor-lpp-not-economically-feasible/5556620002/